Major cost blow out in Snowy Hydro 2.0 scheme

The proposal to build Snowy Hydro 2.0 to strengthen capacity for energy storage seemed like a good idea at first. But as the details of the project emerged, especially the likely direct physical footprint of the project, more and more people and groups started to oppose it. (Background stories on the issue are available here).

After the release of the Environmental Impact Statement (EIS) the NSW National Parks Association said that the plan ‘proposes a completely unacceptable level of damage to Kosciusko National Park’.

However the federal government continues to pursue the proposal. The project received all approvals and is now being constructed.

Now it has emerged that there has been a significant cost blow out in the project, related to one of the major transmission links that is key to deliver its storage services to the rest of the grid.

A new report suggests different that different grid routes could be considered to either save costs, or increase benefits, including a new connection point that will reduce the environment impact on the national park.

Continue reading “Major cost blow out in Snowy Hydro 2.0 scheme”

Traditional owners concerned with plan to dump spoil in Kosciuszko National Park

Threats to the Snowy Mountains continue: Amendments to the Kosciuszko National Park Plan of Management have been published for public feedback, which set out the ‘desired changes’ to the area over the next 40 years (the submission timeline has now closed).

If approved, the plan would see a huge amount of development, including several thousand extra beds in resorts and new areas, occurring within this precious and fragile alpine park.

Meanwhile, Snowy Hydro pushes ahead with its plan to excavate approximately seven million cubic metres of earth for the project’s tunnels and subterranean power station.

That spoil will then be dumped on 55 hectares across four sites within Kosciuszko National Park.

Now a Traditional Owner representing the Ngarigo Nation in southern New South Wales says she has received no consultation about a plan to dump tonnes of waste spoil on her Country.

Continue reading “Traditional owners concerned with plan to dump spoil in Kosciuszko National Park”

14 million cubic metres of spoil to be dumped in Kosciuszko National Park

The proposal to build Snowy Hydro 2.0 to strengthen capacity for energy storage seemed like a good idea at first. But as the details of the project emerged, especially the likely direct physical footprint of the project, more and more people and groups started to oppose it. (Background stories on the issue are available here).

After the release of the Environmental Impact Statement (EIS) the NSW National Parks Association said that the plan ‘proposes a completely unacceptable level of damage to Kosciusko National Park’.

The project received approvals and is now being constructed. However documents tabled in the NSW Legislative Council reveal that the NSW Government will only receive $1.65 million from Snowy Hydro Ltd for the dumping of 14 million cubic metres of spoil in Kosciuszko National Park.

So, a large section of the Kosciuszko National Park (fifty-five hectares) will be impacted by the dumped waste, yet the NSW Government will receive barely 1/1000th of commercial waste disposal rates.

Continue reading “14 million cubic metres of spoil to be dumped in Kosciuszko National Park”

Legal challenge against Snowy 2.0 ?

The proposal to build Snowy Hydro 2.0 to strengthen capacity for energy storage seemed like a good idea at first. But as the details of the project emerged, especially the likely direct physical footprint of the project, more and more people and groups started to oppose it. (Background stories on the issue are available here).

After the release of the Environmental Impact Statement (EIS) the NSW National Parks Association said that the plan ‘proposes a completely unacceptable level of damage to Kosciusko National Park’.

However the federal government continues to pursue the proposal.

In response, it has been announced that the National Parks Association of NSW and ex-Energy Australia chair Ted Woodley are considering a legal challenge to the project, which they say will push back the transition to renewable energy and destroy thousands of hectares of national park.

Continue reading “Legal challenge against Snowy 2.0 ?”

Snowy 2.0 just doesn’t stack up

Earlier this year, it was announced that the next stage of the Snowy Hydro 2.0 expansion had been given the green light, with approval for construction of the project’s ‘Segment Factory’.

Work has now started on the facility: Snowy Hydro has already started clearing native bushland for the construction site at Lobs Hole in the heart of Kosciuszko National Park. The image above (from the NSW NPA) shows work at the Lobs Hole site.

The following is a summary from the NSW National Parks association about why they oppose the Snowy 2.0 development.

Continue reading “Snowy 2.0 just doesn’t stack up”

Approval of Snowy 2.0 EIS sets ‘appalling precedent’

The Snowy Hydro 2.0 expansion started as a good idea. As the scale of the physical impact of the project became more obvious during the approvals process, environmental groups started to oppose it. After the release of the Environmental Impact Statement (EIS) the NSW National Parks Association said that the plan ‘proposes a completely unacceptable level of damage to Kosciusko National Park’.

It has now received planning approval from the NSW state government, despite ongoing objections over the project’s environmental impacts.

Continue reading “Approval of Snowy 2.0 EIS sets ‘appalling precedent’”

Work starts on Snowy Hydro 2.0 ‘Segment Factory’

Back in 2017, the Federal Government announced a feasibility study into the possible expansion to the Snowy Hydro Scheme in the Snowy Mountains of NSW (‘Snowy Hydro 2.0’).  It was billed as being a circuit breaker in the ‘fossil fuels vs renewables’ energy debate because it would be renewable energy that will provide baseload capacity. The project would greatly enhance the pumped hydro capacity of the existing hydro scheme, meaning that water can be used multiple times to produce electricity.

While some environmentalists gave in principle support to the project, many wanted to see the details on what the physical environmental impacts of the project would be. Since then, as the environmental impacts of the project became more obvious, the movement became increasingly opposed.

Recently, a group of energy experts called on the state and federal governments to stop work on the Snowy Hydro 2.0 project.

It has also been reported that the next stage of the Snowy Hydro 2.0 expansion has been given the green light, with approval for construction of the project’s ‘Segment Factory’.

Work has now started on the facility: Snowy Hydro has already started clearing native bushland for the construction site at Lobs Hole in the heart of Kosciuszko National Park.

The NSW National Parks Association says ‘This is just the beginning. Snowy 2.0 will permanently destroy 1000’s of hectares of Kosciuszko, and dump 20 million tonnes of contaminated tunnel spoil, the equivalent of covering Sydney Harbour Bridge and its surrounds’.

The NSW Minister Planning, Rob Stokes, and NSW Minister for the Environment and Energy Matt Kean is expected to make their final decision on approvals for the project ‘any day’.

Check here for additional information on the project from the NSW National Parks Association (NSW NPA).

Take Action

The NSW NPA is asking people to send a letter to the NSW government urging them to not sign off on final environmental approvals.

 

 

 

Snowy Hydro 2.0 gets approval for factory

Just a week or so after a group of energy experts called on the state and federal governments to stop work on the Snowy Hydro 2.0 project, it has been reported that the next stage of the Snowy Hydro 2.0 expansion has been given the green light, with approval for construction of the project’s ‘Segment Factory’.

Continue reading “Snowy Hydro 2.0 gets approval for factory”

Energy experts call for halt to Snowy 2.0

Back in 2017, the Federal Government announced a feasibility study into the possible expansion to the Snowy Hydro Scheme in the Snowy Mountains of NSW.  It was billed as being a circuit breaker in the ongoing impass in the ‘fossil fuels vs renewables’ energy debate because it would be renewable energy that will provide baseload capacity. The project would greatly enhance the pumped hydro capacity of the existing hydro scheme, meaning that water can be used multiple times to produce electricity.

While some environmentalists gave in principle support to the project, many wanted to see the details on what the physical environmental impacts of the project would be. In 2019, the NSW government released the Environmental Impact Statement (EIS) into the project. This showed the level of physical impact of the project. The National Parks Association of NSW said in response that the EIS ‘proposes a completely unacceptable level of damage to Kosciusko National Park’. It has been expected that the project will soon receive approval for its EIS from the NSW government.

Now a group of thirty Australian energy experts have called for a halt to the hydro scheme.

Continue reading “Energy experts call for halt to Snowy 2.0”

A new year, time for new campaign issues?

We still have a long hot dry summer ahead of us. And fires that threaten the mountains that we love so much. But we are also moving towards New Years Eve, when people often make their plans for the coming year.

For me a big part of my planning for the year is to lock in my backcountry trips (here’s my favourite 3 backcountry adventures). Obviously it’s good to have a long think about life, the universe and everything. And then there is activism. 

Sadly, on the activist front there will be lots to do in 2020. Here’s a few ideas on where you may want to put your shoulder to the wheel.

Continue reading “A new year, time for new campaign issues?”

Snowy 2.0 will be ‘Environmental Vandalism’

The NSW government has now released the Environmental Impact Statement (EIS) for the Snowy 2.0 hydro project.

At the core of the Snowy Hydro 2.0 expansion will be the establishment of a new underground tunnel linking the Tantangara and Talbingo reservoirs and the commissioning of a new underground power station that will operate as Australia’s largest pumped hydro energy storage system.

The main works for the Snowy 2.0 project will include the removal of an estimated 9 million cubic meters of excavated rock. The federal government owned Snowy Hydro has proposed that more than half of this excavated material be relocated within either the Talbingo or Tantangara reservoirs, with the remaining material used to establish permanent structures, or for land forming.

While the prospect of a renewed Snowy Hydro scheme, operating as the ‘battery’ for the eastern seaboard, has appeal from a climate angle, it has not – until now – been clear what the physical footprint of the project might be. The EIS outlines the likely direct impacts of the works that would be required under the scheme. The National Parks Association of NSW (NPA) says that the EIS ‘proposes a completely unacceptable level of damage to Kosciusko National Park’.

Continue reading “Snowy 2.0 will be ‘Environmental Vandalism’”

Snowy Hydro seeks ‘fast-tracked environmental approval for pilot works’

We have previously reported that it appeared that Snowy Hydro 2 was seeking to avoid full scrutiny about the likely environmental impacts of the proposal to convert the Snowy Mountains Hydroelectric Scheme into a pumped hydro system.

While the concept itself is an excellent one in that it will provide a huge ‘battery’ of hydro power for the eastern seaboard, it is essential the work be done in a way that minimises impacts on the environment of the Snowy Mountains. (Check here for a summary of possible impacts of the current proposal).

Recent news reports seem to confirm fears that Snowy Hydro is trying to ‘cut corners’ on the approvals process in order to fast track the development.

Continue reading “Snowy Hydro seeks ‘fast-tracked environmental approval for pilot works’”